Not working "Trigger the state transition once all separate assignments..."

Former Member
Former Member
Hi All,

Anyone knows why my workflow does not change to next state even though all assignments have been approved.



This stayed at "Awaiting for Approval" even though all assignments have been approved. It was working a couple of times. Is it any interval for the transmitting?

Thanks
Bin
Parents
  • By default the conditions for triggering state transitions are checked once per hour and the transfer is triggered if the requirements are met. The interval can also be adjusted through a registry setting if needed (restart the server instance after modifying the registry):

    Key path: HKEY_LOCAL_MACHINE\SOFTWARE\Motive\M-Files\\Server\MFServer
    Value name: StateChangerSleepingIntervalInMinutes
    Value type: DWORD
    Value data: default 60, minimum 1

Reply
  • By default the conditions for triggering state transitions are checked once per hour and the transfer is triggered if the requirements are met. The interval can also be adjusted through a registry setting if needed (restart the server instance after modifying the registry):

    Key path: HKEY_LOCAL_MACHINE\SOFTWARE\Motive\M-Files\\Server\MFServer
    Value name: StateChangerSleepingIntervalInMinutes
    Value type: DWORD
    Value data: default 60, minimum 1